Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T12CM07398
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/09/2014 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
12/20/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
12/20/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 3 LIGHT POLE CAISSON FOOTINGS OK TO POUR | |
11/15/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
11/15/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 2 LIGHT POLE CAISSONS - EAST AT GARDEN CENTER - OK TO POUR | |
10/29/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
10/29/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | RAMP AT GL: J/5.3-7 - OK TO POUR PROGRESS AREA | |
10/22/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
10/22/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BAIL, PALLET, & COMPACTOR FOOTING - OK TO POUR | |
10/09/2013 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
09/25/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
09/25/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | WEST FREEZER SLAB; GL: 1-1.25/F-F.8; NW SLAB; GL: D.1-D.2/1.25-1.5; NORTH SLAB; GL: C/2.75-2.5 - OK TO POUR SLABS WHEN PROPER CONCRETE APPROVED | |
09/20/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
09/20/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GL: 8/A-D.1 | |
09/18/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
09/18/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | DOCK LEVELER PITS (3) AS PER DETAIL #10, PAGE S2; 2 EACH EF1/EC1 COLUMN FOOTINGS GL: .75A/H-I.5; OK TO POUR PROGRESS AREAS | |
09/17/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
09/17/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GARDEN CENTER FOOTINGS: GL: A.1/8.25-9; 9/A.1-E.75 - OK TO POUR PROGRESS AREAS; 5 EACH GARDEN CENTER COLUMN FOOTINGS; GL: 8.25/D-E.75 | |
09/16/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
09/16/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 2 LIGHT POLE CAISSONS (NE) - OK TO POUR | |
08/16/2013 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
08/14/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/14/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 3 PEDESTAL COLUMN FOOTINGS - 2 EACH C2/F5A; 1 EACH F5/CC - OK TO POUR PROGRESS AREAS | |
08/13/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/13/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LOADING DOCK WALL FOOTINGS GL: K-L/2-3.5 - OK TO POUR PROGRESS AREAS | |
08/12/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/12/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | WALL & COLUMN FOOTINGS GL: K/4.2 - 3.8 | |
08/09/2013 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
08/08/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/08/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 8 INTERIOR COLUMN FOOTINGS: 4 EACH C1/F1 GL: J/3-2-G/3-2; 2 C1A/F1A GL: 3/F-E; 2 C1B/F1B/E/3-2 - OK TO POUR FOOTINGS | |
08/07/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/07/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LOADING DOCK WALL FOOTINGS: GL: H/7-5.3; 5.3/H-K K/7-5.3; 13 COLUMN FOOTINGS; 3 C8/F8; D/5-4; 2 C6/F6 C/.6-5; 4 C1/F1; 5/H-E.1; 4 C1/F1, 4/H-E.L1 OK TO POUR |
|
08/06/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/06/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMN FOOTINGS - 3 EACH C1/F1 GL: 7/G-E 2 EACH C1/F1A; GL: 6/F-E; 1 C1/F1; GL: 6/G OK TO POUR PROGRESS AREAS |
|
08/05/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/05/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTINGS FOR D & C WALL FOOTINGS GL: 8/G.2-H; H/8-7 OK TO POUR PROGRESS AREA |
|
08/02/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/02/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | WALL FOOTINGS/COLUMN FOOTINGS AT GL: 8/D.1-G; D.1/6.8-8; C/6-6.6-4.7; C/1-4; 1/D.1-J OK TO POUR PROGRESS AREAS |
|
07/31/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
07/31/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CMU WALL FOOTINGS AT GL: 8/D.3-F.6 DETAIL #7/54; REINFORCEMENT SCHEDULE C & D - OK TO POUR PROGRESS AREA |