Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 01/23/2014 |
BUILDING - PROGRESS |
|
Approved |
IVRS - Inspection :* |
| 01/21/2014 |
BUILDING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 01/21/2014 |
BUILDING - PROGRESS |
|
Partial Approval |
ELECTRIC INTERMEDIATE: GFCI'S FOR FLORAL & PRODUCE PREP AREAS; BREAKER REPLACEMENT IN WATER DAMAGED PANEL IN EQUIPMENT ROOM |
| 11/13/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 11/13/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
MENS RESTROOM COMPLETE: ELECTRIC UNDERGROUND 2 1" CONDUITS; PLUMBING UNDERGROUND; 5 IN FLOOR DRAINS/LINES; MECHANICAL - CHILLER LINES FOR FREEZER UNITS - OK TO COVER PROGRESS AREAS |
| 11/07/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 11/07/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
MEN'S RESTROOM PRE SLAB OK TO POUR PROGRESS AREA MASONRY PRE GROUT (IN FILL AT 8') OK TO GROUT |
| 11/06/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 11/06/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
PLUMBING UNDERGROUND FOR MENS RESTROOM - OK TO COVER PROGRESS AREA |
| 11/04/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 11/04/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
INFORMATION ONLY |
| 10/29/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 10/29/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
ELECTRIC: LIGHTING IN MENS RESTROOM |
| 10/28/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 10/28/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
CMU WALLS TOPPED-OUT AT 11'10" - OK TO GROUT PROGRESS AREAS |
| 10/17/2013 |
BUILDING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 10/17/2013 |
BUILDING - PROGRESS |
|
Partial Approval |