Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/26/2012 | MECHANICAL - FINAL | Approved | IVRS - Inspection :* | |
| 09/19/2012 | MECHANICAL - FINAL | Not ready for Inspection | 1. ALL PVC JOINTS ARE TO HAVE PRIMER PRIOR TO GLUE, PRIMER IS TO BE PURPLE IN COLOR PER UPC 2. PVC IS TO BE PROPERLY SUPPORTED STRAPPED IN PVC EXPOSED TO DAYLIGHT IS TO BE COATED FOR U.V PROTECTION 3. PROVIDE FILTERS 4. PROVIDE SECONDARY DRAINS (E-ZTRAP OK ) 5. PROVIDE APPROVED LINE SET INSULATION MIN 3/8' WALL 6. NEUTRAL WIRES NOT BE USED AS HOT LEG 7. ALL ROOD PENETRATIONS ARE TO HAVE APPROVED ROOF JACKS 8. PROVIDE FUSES AT C.V PER UNIT DATA PLATE |