Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/20/2013 | BUILDING - PROGRESS | Approved | ||
| 06/10/2013 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 06/07/2013 | BUILDING - PROGRESS | Partial Approval | SLAB ON GRADE AT SOUTHSIDE | |
| 06/03/2013 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 05/31/2013 | BUILDING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* | |
| 05/31/2013 | BUILDING - PROGRESS | Partial Approval | 5 LIGHT POLE BASES OK | |
| 03/29/2013 | BUILDING - PROGRESS | Denied | IVRS - Inspection : See detailed listing on site.| 999* POST YOUR ADDRESS PROVIDE PLANS |