Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 02/05/2013 |
PLUMBING - INTERMEDIATE |
|
Approved |
PER PLUMBING FINAL |
| 11/14/2012 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
1. Shower pan OK. Plan doesn't show what type of flooring is being used in the bathroom. Closet flange is to sit on top of the floor. |
| 09/20/2012 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
1. Need to see the closet flange. 2. Contractor needs hand out for shower pans. |