Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/05/2013 | ENGINEERING - FINAL | Approved | ||
| 03/04/2013 | ENGINEERING - FINAL | Continued | PRE-FINAL WALK THROUGH WITH SUPERINTENDENT. NO SIGNIFICANT ISSUES, NEED TO COMPLETE SITE WORK 100% |
|
| 11/29/2012 | ENGINEERING - FINAL | Continued | INSPECTED STORM DRAIN PIPING AROUND BLDG. 8/4/3" PVC W/ CLEANOUTS AND CONNECTIONS TO THE ROOF DRAINS AND A BUBBLER BOX LOCATED IN THE RET BASIN. OK TO COVER |
|
| 11/28/2012 | ENGINEERING - FINAL | Continued | 1) INSPECTED STORM PIPE BEING INSTALLED ALONG SOUTH SIDE OF SITE. 2) PIPE CONNECTED TO A BUBBLER BOX LOCATED IN THE RET/DET BASIN. OK TO COVER 3) REPAIR SILT FENCE AND REMOVE MATERIAL FROM ONTOP OF FENCE. 4) SWEEP UP TRACKED SOIL. |