Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/06/2013 | BUILDING - PROGRESS | Approved | IVRS - Inspection :* | |
| 02/15/2013 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* APRON SLABS- NE AND EAST AREAS OK TO POUR PROGRESS AREAS | |
| 02/14/2013 | BUILDING - PROGRESS | Partial Approval | APRON SLABS-WEST SIDE AT LIGHT POLES SLAB BETWEEN BUILDING AND CANOPY -OK TO POUR INSPECTION PERFORME |
|
| 02/12/2013 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 02/11/2013 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :*MAIN ENTRY SLABS; NORTH CURBS AT CANOPY AREA- OK TO POUR SLABS | |
| 02/05/2013 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :*APRON SLABS; MAIN ENTRY TO BUILDING, 2 SLABS AT WEST PORTION OF SITE DOWELS AND REINFORCEMENT IN PLACE- OK TO POUR PROGRESS AREAS. 2) PANEL CC INSIDE BUILDING OK PANEL DD, C,D |