Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/12/2012 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
| 09/06/2012 | REINFORCED MASONRY PRE-GROUT | Partial Approval | OK TO POUR LINTELS AT FRONT OF BLDG. | |
| 09/05/2012 | REINFORCED MASONRY PRE-GROUT | Partial Approval | FINAL LIFT AT COLUMNS OK | |
| 09/04/2012 | REINFORCED MASONRY PRE-GROUT | Partial Approval | OK. 1ST LIFT AT VESTIBULE | |
| 08/30/2012 | REINFORCED MASONRY PRE-GROUT | Partial Approval | * OK TO LINTERS AT SOUTH AND NORTH *OK TO UNDERGROUND CONDUITS FOR CUSTOMER SERVICE DESK TO COVER |
|
| 08/28/2012 | REINFORCED MASONRY PRE-GROUT | Partial Approval | REBAR EPOXY INTO EXISTING STEM WALL AT SOUTHSIDE OF BUILDING CONTRACTOR HAS SPECIAL INSPECTION REPORT |