Permit: T12CM02811

Parcel: 115044910


Addresses:

1020 N TYNDALL AV

Inspection Status: Approved

Inspection History: PLUMBING - INTERMEDIATE

Date Description Inspector Results Comments
07/18/2013 PLUMBING - INTERMEDIATE Approved IVRS - Inspection :*
03/25/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
03/21/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
03/19/2013 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
03/18/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*SOUTH SIDE RDC, WASTE AND VENT
03/12/2013 PLUMBING - INTERMEDIATE Partial Approval LEVEL 13 NORTH DONE AND VENT
03/08/2013 PLUMBING - INTERMEDIATE Partial Approval DOM WASTE AND VENT SOUTH AND EAST 13TH FLOOR
03/05/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :* PARTIAL 8TH FLOOR PROGRESS
03/04/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :* 12TH FLOOR WASTE AND VENT
02/26/2013 PLUMBING - INTERMEDIATE Partial Approval PARTIAL 11TH FLOOR NORTH VENTS AND WASTE DOWN
02/25/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
02/13/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
02/08/2013 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
02/07/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*ROOF DRAINS ON 4TH FLOOR OK.
02/06/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
02/05/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*LEVEL 9 NORTH SIDE HYDRO
02/04/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :* SOUTH HALF ON LEVEL 9 OK TO ONE SIDE 9 LEVEL ROOM
02/01/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :* THRU FLOOR PENETRATION
01/31/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :* ROOF DRAIN ON 8TH FLOOR OK
01/30/2013 PLUMBING - INTERMEDIATE Partial Approval HYDRO ON 8TH NORTH VENT & DOMESTIC
01/29/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
01/28/2013 PLUMBING - INTERMEDIATE Partial Approval THUR FLOOR PENETRATION OK ON 11TH FLOOR
01/22/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :* THUR FLOOR PENETRATION
01/18/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :* 9TH FLOOR NORTH TEST. LEVEL 9 THUR FLOOR PENETRATION.
01/16/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
01/10/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
01/09/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :* 8TH FLOOR THRU FLOOR PENETRATION
01/08/2013 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
01/07/2013 PLUMBING - INTERMEDIATE Partial Approval 6TH FLOOR TEST OK EXCLUDES NORTH SIDE
01/03/2013 PLUMBING - INTERMEDIATE Partial Approval 5TH FLOOR NORTH IN WALLS VENT AND WATER OK
01/02/2013 PLUMBING - INTERMEDIATE Partial Approval 5TH SOUTH TEST ON VENT
7TH FLOOR THRU FLOOR PENETRATIONS
12/26/2012 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
12/21/2012 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
12/19/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
12/18/2012 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
12/17/2012 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
12/14/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
12/12/2012 PLUMBING - INTERMEDIATE Partial Approval 4TH LEVEL OK
12/11/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
12/10/2012 PLUMBING - INTERMEDIATE Partial Approval 4TH FLOOR PENETRATIONS THRU FLOOR
12/07/2012 PLUMBING - INTERMEDIATE Partial Approval ROOF DRAINS NORTH SIDE LEVELS 1-4 OK 2, 2ND FLOOR PENETRATION THUR FLOOR ONLY
12/06/2012 PLUMBING - INTERMEDIATE Partial Approval LEVELS 2-3 FLOOR PENETRATION
12/05/2012 PLUMBING - INTERMEDIATE Partial Approval DWV AND POTABLE FOR LEVEL 4
ALL IN WALL LEVEL 3 & 2
12/03/2012 PLUMBING - INTERMEDIATE Partial Approval 4TH FLOOR DWV FOR SOUTH AND EAST WINGS.

2ND FLOOR LEAK REPAIRS MADE.
11/30/2012 PLUMBING - INTERMEDIATE Partial Approval 6TH & 7TH ROOF DRAIN TEST