Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
Permit Number - T12CM02811
Inspection Description - BUILDING PRE-SLAB
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/18/2013 | BUILDING PRE-SLAB | Approved | IVRS - Inspection :* | |
03/20/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*1ST AND 2ND FLOOR INFALL FROMCRANE PARTIAL ON PARAPET RAMP AND STAIRS AT POOL | |
03/19/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
03/06/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*POOL DECK OK | |
03/05/2013 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
03/04/2013 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
02/28/2013 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
02/25/2013 | BUILDING PRE-SLAB | Not ready for Inspection | NOT READY PARTIAL 2ND FLOOR CORRIDORS AND 6GTH FLOOR ROOOMS | |
01/02/2013 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
12/20/2012 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* HOUSE KEEPING PADS ON ROOF | |
12/05/2012 | BUILDING PRE-SLAB | Partial Approval | STRUCTURAL FOR ROOF COMPLETE | |
11/27/2012 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
11/16/2012 | BUILDING PRE-SLAB | Partial Approval | 14th level north partial welding on north stairway 1-6 | |
11/13/2012 | BUILDING PRE-SLAB | Partial Approval | SOUTH POUR LEVEL 14 | |
11/09/2012 | BUILDING PRE-SLAB | Partial Approval | NORTH 1/2 LEVEL 13 | |
11/06/2012 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
11/02/2012 | BUILDING PRE-SLAB | Partial Approval | 12TH FLOOR NORTH | |
10/30/2012 | BUILDING PRE-SLAB | Partial Approval | SHEARWALL 6 11TH LEVEL | |
10/26/2012 | BUILDING PRE-SLAB | Partial Approval | 11 level north ok | |
10/23/2012 | BUILDING PRE-SLAB | Partial Approval | SOUTH POUR 11 LEVEL | |
10/16/2012 | BUILDING PRE-SLAB | Partial Approval | SOUTH POUR 10 LEVEL OK | |
10/12/2012 | BUILDING PRE-SLAB | Partial Approval | NORTH POUR 9TH LEVEL | |
10/09/2012 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
10/05/2012 | BUILDING PRE-SLAB | Partial Approval | 8TH LEVEL NORTH. | |
10/02/2012 | BUILDING PRE-SLAB | Partial Approval | SOUTH POUR 8TH LEVEL | |
09/28/2012 | BUILDING PRE-SLAB | Partial Approval | LEVEL 7 NORTH | |
09/25/2012 | BUILDING PRE-SLAB | Partial Approval | LEVEL 2 SOUTH POWER | |
09/21/2012 | BUILDING PRE-SLAB | Partial Approval | LEVEL 6 NORTH 1/2 | |
09/17/2012 | BUILDING PRE-SLAB | Partial Approval | NORTH 1/2 LEVEL 5 OK | |
09/11/2012 | BUILDING PRE-SLAB | Partial Approval | SOUTH 1/2 LEVEL 5 | |
09/10/2012 | BUILDING PRE-SLAB | Partial Approval | SOG ELEVATOR AND STAIR | |
09/07/2012 | BUILDING PRE-SLAB | Partial Approval | 4TH LEVEL NORTH | |
08/31/2012 | BUILDING PRE-SLAB | Partial Approval | LEVEL 4 SOUTH GL 6-9/A-E |