Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 11/26/2012 |
PLUMBING - ROUGH, SOIL |
|
Approved |
|
| 08/31/2012 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
1. At shower- vent to be rolled up at a 45 degree before returning to horizontal. No change required, installed per IPC. 2. Require a shielded coupling at the bldg. connection. 3. Protect the copper srevice passing through the fitting. 4. Reinspected 12:50 pm. Corrections made OK-ready for concrete |