Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/25/2012 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 05/24/2012 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1) COMPLY WITH PREVIOUS NOTES 2) CLAY PIPE OK PER LEERAY HANLY |
|
| 05/23/2012 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1) AT WATER CLOSET: WHERE IS VENT CONNECTS TO A HORIZONTAL DRAIN, IT SHALL HAVE ITS INVERT TAKEN OFF ABOVE THE DRAINAGE CENTER LINE, DOWN STREAM OF THE TRAP. EACH VENT SHALL RISE VERTICALLY, TO A POINT NOT LESS THAN 6" ABOVE THE FLOOD RIM BEFORE OFF SETTING HORIZONTALLY 2) AT SHOWER: EACH FIXTURE TRAP TO HAVE VENT. A DRAIN MAY NOT DAMP INTO A VENT 3) A FURNCO MAY NOT BE USED UNDER THE FLOOR 4) CLAY PIPE IS NOT PERMITTED UNDER THE FLOOR |
|
| 05/21/2012 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* |