Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/28/2012 | BUILDING - FINAL | Approved | IVRS - Inspection :* | |
| 06/27/2012 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 05/31/2012 | BUILDING - FINAL | Partial Approval | IVRS - Inspection :* 1) FINISH #1 & 5 |
|
| 05/22/2012 | BUILDING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) PV BREAKER TO BE PER 690.64 (B) THIS IS A 200 AMP BUSS MAIN TO BE FURTHER TEST POSITION FROM MAIN 2) LABELS PER 690.17 AT INVERTERS AND ALL DISCONNECTS 3) LABEL INVERTERS AND PANEL TO MATCH 4) GROUNDING ELECTRODE CONDUCTOR TO TERMINATE AT MARKED TERMINAL AT INVERTERS 5) PROPERLY SUPPORT CONDUIT TO WALL WEST SIDE 6) PLEASE PROVIDE LADDER FOR ROOF ACCESS 7) SUPPORT ARRAY DISCONNECT UP UNDER PANELS |