Permit: T12CM00380

Parcel: 135074470


Addresses:

1470 S EASTSIDE LP

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
08/11/2014 ENGINEERING - FINAL Approved PHASE II COMPLETED
12/18/2013 ENGINEERING - FINAL Continued INSPECTED SCUPPER AND SIDEWALK INSTALL ALONG NE CORNER OF SITE - SCUPPER PER COT DEV STD 205 AND THE APPROVED PLANS - OK TO POUR CONCRETE
11/27/2013 ENGINEERING - FINAL Continued INSPECTED FORMS FOR SIDEWALK IN FRONT OF NEW BLDG.
SIDEWALK HAS BEEN CONSTRUCTED PER APPROVED PLAN.
PROJECT IS PHASE II OF A THREE PHASE DEVELOPMENT.
PROJECT HAS A DEVELOPMENT PLAN AND PERMIT NUMBER (DP11-0034).
ENSURE SITE WORK IS CONSTRUCTED PER APPROVED PLAN