Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 08/01/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
IVRS - Inspection :* |
| 04/10/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection :* |
| 04/10/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
COLUMN FOOTINGS: 2 EACH C4/F5; 1 EACH C6/F4; 5 C2/F6; OK TO POUR PROGRESS AREAS |
| 04/04/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection :* 2 CAISSON COLUMN FOOTINGS AS PER TOWER INSTALL PLANS- 90MPH ASSEMBLY OK TO POUR |
| 03/22/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
4 LIGHT POLE CAISSONS- OK TO POUR PROGRESS AREA |
| 10/15/2012 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
7 EACH C2/F6 COLUMN FOOTINGS OK TO POUR PROGRESS AREAS |