Permit: T12CM00125

Parcel: 12701003S


Addresses:

250 N ARCADIA AV


Inspection Status: Not ready for Inspection

Inspection History: PLUMBING - PROGRESS

Permit Number - T12CM00125

Inspection Description - PLUMBING - PROGRESS

Inspection Status - Not ready for Inspection

Date Description Inspector Results Comments
09/25/2012 PLUMBING - PROGRESS Not ready for Inspection IVRS - Inspection :*
07/02/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
06/29/2012 PLUMBING - PROGRESS Not ready for Inspection IVRS - Inspection :*
06/22/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
06/21/2012 PLUMBING - PROGRESS Not ready for Inspection IVRS - Inspection :*
06/18/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
06/14/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
06/13/2012 PLUMBING - PROGRESS Partial Approval 1. Piping between bldg. ten and eleven - tie-ins made on buildings eleven and twelve, OK to cover. 2. Mains for building thirteen and fourteen OK to foam.
06/01/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
05/11/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
05/04/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
04/20/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
04/13/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
03/16/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
03/15/2012 PLUMBING - PROGRESS Not ready for Inspection IVRS - Inspection :*
03/12/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
03/09/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
02/23/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
1) LETTER FROM PH MECH ENG ALLOWING 1" THICK FOAM INSULATION
02/17/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
02/10/2012 PLUMBING - PROGRESS Denied IVRS - Inspection :
See detailed listing on site.| 999*
1) 1 1/2" MINIMUM INSULATION REQUIRED
02/10/2012 PLUMBING - PROGRESS Partial Approval IVRS - Inspection :*
1) AFTER HOURS INSPECTION REQUIRED BY STACEY AT 297-2775
2) PAID WITH CHECK #4839
3) TRON MECHANICAL-KENT 403-0793
4) PIPE INSULATION FOR B3 AND PART OF B4 OK TO COVER