Inspection Status: Approved

Inspection History: PLUMBING - YARD WTR LINE/TEST

Permit Number - T12CM00125

Inspection Description - PLUMBING - YARD WTR LINE/TEST

Inspection Status - Approved

Date Description Inspector Results Comments
09/25/2012 PLUMBING - YARD WTR LINE/TEST Approved IVRS - Inspection :*
07/02/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval 1. Bldg #3 tie ins and foamed OK 2. Bldg. #14 foamed. Tie ins made. OK to cover. 3. Bldg. #6 RPPBP 2" OK to cover. 4. Bldg #7 RPPBP 2" OK to cover.
06/29/2012 PLUMBING - YARD WTR LINE/TEST Not ready for Inspection IVRS - Inspection :*
06/22/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval 1. CPVC mains nfor building fourteen installed Ok. OK to foam.
06/21/2012 PLUMBING - YARD WTR LINE/TEST Not ready for Inspection 1. No message left. Nobody at the trailer. Unable to locate plumber.
06/18/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval 1. Building thirteen- tie ins made. OK to cover all areas.
06/14/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval 1. Bldg. ten tie-ins made and branches foamed. Buildings four, five, six, nine, and fifteen tie-ins made and branches foamed.
06/13/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval IVRS - Inspection :*
06/01/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval IVRS - Inspection :*
1) BLDG 1 YARD LINE "H" AND "C" TEST AND INSULATION OK, OK TO BACKFILL
2) OFFICE YARD LINE "H" AND "C" TEST AND INSULATION OK TO BACKFILL
3) BLDG 12-MAINS FOM 12 TO BLDG 14 TEST OK, OK TO INSULATE H.W. SIDE
05/11/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval IVRS - Inspection :*
05/04/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval IVRS - Inspection :*
1) TIE INS FOR BLDGS #8, 2 AND 7 MADE OK
04/20/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval IVRS - Inspection :*
1) BLDG 7 MAINS OK TO COVER
2) 2 1/2" CW MAIN FROM SOUTHEAST CORNER OF 9 TO BOILER ROOM
04/13/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval IVRS - Inspection :*
1) MAIN NORTH OF LAUNDRY AND BLDG 8 PIPE AND INSULATION
03/19/2012 PLUMBING - YARD WTR LINE/TEST Not ready for Inspection IVRS - Inspection :*
03/16/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval IVRS - Inspection :*
1) BLDG 1 AND OFFICE ALL PIPING FOAMED, OK TO COVER
03/15/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval IVRS - Inspection :*
1) 1" TO OFFICE , RED LINE PLAN
03/12/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval IVRS - Inspection :*
1) OK TO COVER FOAMED PIPING ON NORTH LOOP
03/09/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval IVRS - Inspection :*
1) NORTH LOOP AROUND OFFICE, BLDG 1 AND BLDG 2 OK TO COVER AFTER FOAMED
02/24/2012 PLUMBING - YARD WTR LINE/TEST Not ready for Inspection IVRS - Inspection :*
02/23/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval IVRS - Inspection :*
1) BLDG MAINS 4 & 6 WITH TEST AND INSULATION OK
02/17/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval IVRS - Inspection :*
1) BLDG 4, 5 & 6 PIPING MAINS
2) INSULATION 4 & 5
02/10/2012 PLUMBING - YARD WTR LINE/TEST Not ready for Inspection IVRS - Inspection :*
02/08/2012 PLUMBING - YARD WTR LINE/TEST Partial Approval IVRS - Inspection :*
MAINS FOR BUILDINGS #4. 5 & 3 OK TO INSULATE