Inspection Status: Approved
Inspection History: PLUMBING - YARD WTR LINE/TEST
Permit Number - T12CM00125
Inspection Description - PLUMBING - YARD WTR LINE/TEST
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/25/2012 | PLUMBING - YARD WTR LINE/TEST | Approved | IVRS - Inspection :* | |
07/02/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | 1. Bldg #3 tie ins and foamed OK 2. Bldg. #14 foamed. Tie ins made. OK to cover. 3. Bldg. #6 RPPBP 2" OK to cover. 4. Bldg #7 RPPBP 2" OK to cover. | |
06/29/2012 | PLUMBING - YARD WTR LINE/TEST | Not ready for Inspection | IVRS - Inspection :* | |
06/22/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | 1. CPVC mains nfor building fourteen installed Ok. OK to foam. | |
06/21/2012 | PLUMBING - YARD WTR LINE/TEST | Not ready for Inspection | 1. No message left. Nobody at the trailer. Unable to locate plumber. | |
06/18/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | 1. Building thirteen- tie ins made. OK to cover all areas. | |
06/14/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | 1. Bldg. ten tie-ins made and branches foamed. Buildings four, five, six, nine, and fifteen tie-ins made and branches foamed. | |
06/13/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* | |
06/01/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* 1) BLDG 1 YARD LINE "H" AND "C" TEST AND INSULATION OK, OK TO BACKFILL 2) OFFICE YARD LINE "H" AND "C" TEST AND INSULATION OK TO BACKFILL 3) BLDG 12-MAINS FOM 12 TO BLDG 14 TEST OK, OK TO INSULATE H.W. SIDE |
|
05/11/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* | |
05/04/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* 1) TIE INS FOR BLDGS #8, 2 AND 7 MADE OK |
|
04/20/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* 1) BLDG 7 MAINS OK TO COVER 2) 2 1/2" CW MAIN FROM SOUTHEAST CORNER OF 9 TO BOILER ROOM |
|
04/13/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* 1) MAIN NORTH OF LAUNDRY AND BLDG 8 PIPE AND INSULATION |
|
03/19/2012 | PLUMBING - YARD WTR LINE/TEST | Not ready for Inspection | IVRS - Inspection :* | |
03/16/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* 1) BLDG 1 AND OFFICE ALL PIPING FOAMED, OK TO COVER |
|
03/15/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* 1) 1" TO OFFICE , RED LINE PLAN |
|
03/12/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* 1) OK TO COVER FOAMED PIPING ON NORTH LOOP |
|
03/09/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* 1) NORTH LOOP AROUND OFFICE, BLDG 1 AND BLDG 2 OK TO COVER AFTER FOAMED |
|
02/24/2012 | PLUMBING - YARD WTR LINE/TEST | Not ready for Inspection | IVRS - Inspection :* | |
02/23/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* 1) BLDG MAINS 4 & 6 WITH TEST AND INSULATION OK |
|
02/17/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* 1) BLDG 4, 5 & 6 PIPING MAINS 2) INSULATION 4 & 5 |
|
02/10/2012 | PLUMBING - YARD WTR LINE/TEST | Not ready for Inspection | IVRS - Inspection :* | |
02/08/2012 | PLUMBING - YARD WTR LINE/TEST | Partial Approval | IVRS - Inspection :* MAINS FOR BUILDINGS #4. 5 & 3 OK TO INSULATE |