Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 02/26/2013 |
PLUMBING - PROGRESS |
|
Approved |
|
| 02/01/2013 |
PLUMBING - PROGRESS |
|
Partial Approval |
1. Sheet PS1.0 (unstamped) pump discharge drain for sump to POC with existing 4" OK. 2" PVC w/tracer OK to cover. Sump not installed. |
| 12/14/2012 |
PLUMBING - PROGRESS |
|
Partial Approval |
1. Interior plumbing OK. Received approved site plan. |
| 12/13/2012 |
PLUMBING - PROGRESS |
|
Not ready for Inspection |
|
| 11/21/2012 |
PLUMBING - PROGRESS |
|
Partial Approval |
1. Will require an approved site utility plan. (Development Package) Not installed per plan. No redlines for water reroute. One inch PVC yardwater with tracer extended from P.O.C. with existing to bldg. shut off, Ok to cover subject to approved plan. Two inch ABS sewer extended twenty feet from bldg. OK. |