Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T12BU00546
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/29/2013 | GRADING - INTERMEDIATE | Approved | ||
07/10/2013 | GRADING - INTERMEDIATE | Continued | 1) PRIOR TO FINAL APPROVAL, CLEAN OUT RET/DET BASIN OF CONCRETE AND CONSTRUCTION MATERIALS 2) CLEAN OUT CATCH BASINS 3) LOWER TWO WALL OPENINGS IN THE PARKING LOT |
|
06/26/2013 | GRADING - INTERMEDIATE | Continued | NO CHANGES AND/OR CONCERNS AT THIS TIME | |
06/20/2013 | GRADING - INTERMEDIATE | Continued | NO SIGNIFICANT CONCERNS AT THIS TIME CONTRACTOR PAVING PARKING LOT TODAY NO SIGNIFICANT STORM WATER CONCERNS |
|
06/05/2013 | GRADING - INTERMEDIATE | Continued | DISCUSSED PERMIT REQUIREMENTS AND TRASH ENCLOSURE DETAILS ON PLANS. NO SIGNIFICANT CHANGES AND/OR CONCERNS AT THIS TIME. |
|
06/04/2013 | GRADING - INTERMEDIATE | Continued | SITE HAS BEEN PHASED. 1ST PHASE WAS CONSTRUCTION OF THE SAUSAGE DELI, PHASE TWO IS CONSTRUCTION OF THE WALGREENS. DIFFERENT CONTRACTOR FOR EACH PHASE. 1) THERE ARE TWO DETAILS FOR TRASH ENCLOSURE FOR THE WALGREENS. ONE ON THE ARCH PLANS AND ONE ON THE CIVIL PLANS. PROVIDE INFO FROM THE ENG OF RECORD AND USE ONE DETAIL. 2) ENSURE SITE IS SLOPED AND GRADED PER APPROVED PLANS - PAVING IN TWO WEEKS 3) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
|
01/07/2013 | GRADING - INTERMEDIATE | Continued | REVIEWED DRAWINGS, WALKED SITE WITH SUPERINTENDENT. NO SIGNIFICANT CONCERNS AND/OR CHANGES AT THIS TIME |
|
10/03/2012 | GRADING - INTERMEDIATE | Continued | SITE VISIT ONLY, SITE NOT READY AT THIS TIME. | |
07/30/2012 | GRADING - INTERMEDIATE | Continued | NO WORK ON THIS SITE AT THIS TIME. IT APPEARS THAT THE CREW HAS CONSTRUCTED THE PAD AND HAVE MOVED TO ANOTHER SITE. | |
07/27/2012 | GRADING - INTERMEDIATE | Continued | CREWS WORKING ON PROCESS MATERIAL AND PREPARING THE SUBGRADE FOR COMPACTION IN THE AREA WHERE THE NEW BUILDING FOUNDATION IS TO BE PLACED. | |
07/20/2012 | GRADING - INTERMEDIATE | Partial Approval | THE DEMOLITION OF THE SITE HAS BEEN COMPLETED AT THIS TIME, THEY WILL START CONSTRUCTING THE NEW BUILDING STARTING NEXT WEEK. |