Permit: T12BU00348

Parcel: 14044007E

Inspection Status: Approved

Inspection History: GRADING - FINAL

Permit Number - T12BU00348

Inspection Description - GRADING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
06/11/2020 GRADING - FINAL Approved
10/06/2015 GRADING - FINAL Not ready for Inspection PRIOR TO FINAL APPROVAL PROVIDE THE FOLLOWING:

1) EL-CERT/FLOODPLAIN USE PERMIT
2) CERT STATEMENT FROM THE ENG OF RECORD
3) PROVIDE AN AS-BUILT PLAN FOR FINAL INSPECTION
4) ENSURE CHANGES MADE AND SHOWN ON PLANS HAVE BEEN APPROVED BY THE COT
5) COMPLETE ALL ASPECTS OF PHASE I SHOWN ON THE APPROVED PLANS
08/21/2015 GRADING - FINAL Continued 1) LOOKED AT SPILLWAY ALONG THE NE CORNER OF SITE. RE-BAR INSTALLED AND FORMED PER APPROVED PLANS - OK TO POUR
2) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
08/13/2015 GRADING - FINAL Continued 1) NOT READY FOR FINAL APPROVAL.
2) COMPLY WITH CONDITION NUMBER 11 UNDER FLOOD PLAIN USE PERMIT #T12OT00427 : (As-builts shall be submitted under the grading permit activity number T12BU00348 to PDSD Permit Clerks as a Final Revised Grading Plan package. This package shall include: cover letter with summary description of any changes to project, 2 copies of only those sheets that have as-built changes, substantial completion letters from EOR and soils engineer. As-built data shall include as-built FFE's for all constructed buildings, as-built elevations for inverts of drainage systems, and other general as-built spot elevations as deemed necessary by RLS.)
AND CALL FRO RE-INSPECTION
3) REPAIR EROSION DAMAGE
07/27/2015 GRADING - FINAL Not ready for Inspection COMPLET NOTES FROM 5-29-2015.
05/29/2015 GRADING - FINAL Continued 1) CHECK FOR EL-CERT/FLOODPLAIN USE PERMIT
2) CERT STATEMENT FROM THE ENG OF RECORD
3) PROVIDE AN AS-BUILT PLAN FOR FINAL INSPECTION
4) ENSURE CHANGES MADE AND SHOWN ON PLANS HAVE BEEN APPROVED BY THE COT
5) COMPLETE ALL ASPECTS OF PHASE I SHOWN ON THE APPROVED PLANS