Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T12BU00348
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/13/2015 | GRADING - INTERMEDIATE | Approved | ||
| 05/06/2015 | GRADING - INTERMEDIATE | Continued | FOLLOW UP INSPECTION, NO CHANGES AND/OR CONCERNS AT THIS TIME | |
| 04/28/2015 | GRADING - INTERMEDIATE | Continued | NO SITE CHANGES AND/OR CONCERNS AT THIS TIME | |
| 04/14/2015 | GRADING - INTERMEDIATE | Continued | 1) WALKED SITE WITH SUPERINTENDENT, REVIEWED PLANS 2) MEASURED SLOPE FOR SIDEWALKS THAT HAVE BEEN COMPLETED 3) DISCUSSED ANY CHANGES TO ORIGINAL PLAN 4) PROVIDE AS-BUILT AND CERT STATEMENT |
|
| 04/03/2015 | GRADING - INTERMEDIATE | Continued | 1) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME 2) ANY SIGNIFICANT SITE CHANGES MUST BE SHOWN ON AN APPROVED REVISION |
|
| 03/26/2015 | GRADING - INTERMEDIATE | Continued | 1) TRUNCATED DOMES ARE NOT REQUIRED AT THIS SITE PER MARTY DUPONT, COT ADA COMPLIANCE SPECIALIST/CARL BUETER, P.E. AND ADASAD. 2) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
|
| 02/26/2015 | GRADING - INTERMEDIATE | Continued | 1) WALKED SITE WITH SUPERINTENDENT DISCUSSED APPROVED GRADING PLAN AND STORM WATER REQUIREMENTS 2) PEDESTRIAN ACCESS BEING CONSTRUCTED AND SOME CURB AND CONCRETE SITE WORK BEING INSTALLED. 3) RETENTION/DETENTION BASINS HAVE BEEN ROUGHED-IN 4) WILL FOLLOW UP AS MORE SITE WORK IS BEING ACCOMPLISHED. 5) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
|
| 02/25/2015 | GRADING - INTERMEDIATE | Continued | 1) MET WITH SUPERINTENDENT TO DISCUSS SITE/GRADING 2) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
|
| 01/20/2015 | GRADING - INTERMEDIATE | Continued | 1) INSPECTED INSTALL OF PVC-STORM PIPE AND HDPE PIPE @ DRAINAGE CHANNEL/BASIN. 2) PVC PIPE FOR FUTURE USE 3) STORM PIPE INSTALLED PER APPROVED PLANS. 4) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME OK TO COVER PIPE (PICTURES TAKEN) |
|
| 12/23/2014 | GRADING - INTERMEDIATE | Continued | 1) INSPECTED PEDESTRIAN ACCESS RAMP TO SCALE BLDG. RAMP FORMED PER PLAN - OK TO POUR CONCRETE. 2) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. |
|
| 12/19/2014 | GRADING - INTERMEDIATE | Continued | NO CHANGES NO CONCERNS | |
| 12/18/2014 | GRADING - INTERMEDIATE | Continued | ||
| 11/14/2014 | GRADING - INTERMEDIATE | Continued | NO CHANGES AND/OR CONCERNS AT THIS TIME | |
| 11/05/2014 | GRADING - INTERMEDIATE | Continued | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME NO SITE/GRADING CONCERNS |