Inspection Status: Partial Approval
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/19/2011 | PLUMBING - FINAL | Partial Approval | IVRS - Inspection :* 1) 12 PSI TEST IS OK, OK TO BACKFILL TRENCH 2) PROVIDE MINIMUM 3 SCREWS IN ALL JOINTS OF WATER HEATER VENT CONNECTOR 3) PROVIDE THE REQUIRED ELECTRIC BOND TO THE METALLIC GAS PIPING 4) RESCHEDULE FOR FINAL INSPECTION |
|
| 09/16/2011 | PLUMBING - FINAL | Cancelled | IVRS - RI canceled 1) TEST TO HAVE MINIMUM 10 PSI AND HOLD FOR 15 MINUTES WITH NO LOSS OF PRESSURE 2) TEST TO BE ON ENTIRE SYSTEM 3) PROVIDE A TEMPERATURE AND PRESSURE RELIEF DRAIN, GRAVITY DRAIN TO DAYLIGHT 4) PROVIDE FASTENERS AT WATER HEATER/FURNACE VENT CONNECTORS 5) PROVIDE BONDING OF BLDG GAS SYSTEM |