Inspection History Details
Inspection Status: Approved
Inspection History: SITE - SEWER
Permit Number - T11PL01362
Inspection Description - SITE - SEWER
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/11/2012 | SITE - SEWER | Approved | IVRS - Inspection :* | |
11/14/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) 4" TIE IN FOR NEW BLDG SANITARY 2) 4" TIE IN FOR EXISTING NEUTRALIZATION TANK 3) 6" TIE IN FOR EAST BLDG SANITARY UPSTREAM OF MH #4 OK |
|
10/13/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) VACUUM TESTING MANHOLE #1, 2, 3 & 4 OK |
|
10/12/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) MIRROR AND MANDREL OK 2) AIR TEST MANHOLES #1 TO 2, 2 TO 3, 3 TO 4, AND 6" FROM #4 TO EXISTING ALL OK |
|
10/11/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
10/07/2011 | SITE - SEWER | Partial Approval | 1) 6" SDR FROM MANHOLE #4 UPSTREAM TO 2' FROM EXISTING 6", 4" HCS STUB 7' OUT OF MANHOLE #4 8" FROM MANHOLE #3 TO MANHOLE #4, MANHOLE #4 BASE POURED AND STACKED | |
10/06/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* EXCAVATION OF NEW LOCATION FOR MARITECE??? #4 EXCAVATION 4" BLD HCS & 6" GOIAB??? EAST PER REVISED PCDOQ PLAN, SERVING AS ROD LINE AWAITING COT APPROVAL |
|
09/28/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) 4" SDR HCS LATERAL APP 40' GOING SOUTH BETWEEN MANHOLE #2 AND MANHOLE #3 |
|
09/27/2011 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* 1) NO CHANGES 2) CITY OF TUCSON WILL INSPECT 3" YARD LINE |
|
09/26/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) 8" 26' UPSTREAM FROM MANHOLE #3 WITH BASE POURED EXCAVATION FOR HCS CENTER OF BLDG |
|
09/23/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* MANHOLE #3 UPSTREAM 8" SDR 35 INSTALLED PLUS OR MINUS 40' WITH TRACER |
|
09/22/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) 8" TO MANHOLE #3, BASE EXCAVATED CONTINUES TOWARDS #4 |
|
09/21/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) POT HOLING UTILITIES |
|
09/20/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) 8" SDR CONTINUES TOWARD MANHOLE #3 APP. 200' FROM MANHOLE #2 BEDDING,LAYING,TRACER AND SHADING |
|
09/19/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) 8" SDR CONTINUES APP. 140' FROM MANHOLE #2 TOWARD MANHOLE #3 BEDDING, LAYING, TRACER AND SHADING |
|
09/16/2011 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* 1) CANCELLED |
|
09/15/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) MANHOLE #1 & 2 STACKED 2) BACK FILLING BETWEEN 2 & 3 3) NO NEW PIPING |
|
09/14/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) MANHOLE #1 + #2 BASES POURED, BEDDING, LAYING, SHADING TRACER APP. 60' GOINT EAST FROM MANHOLE #2 TOWARD MANHOLE #3 |
|
09/13/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) PREPING FOR MANHOLE #1 BASE AND MANHOLE #2 BASE PIPING IS REMOVED BETWEEN MANHOLE #2 & MANHOLE #3 DUT TO WATER. EXCAVATION TO BEGIN AGAIN #2 TO #3 P.M. TODAY |
|
09/12/2011 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* 1) CANCELLED |
|
09/09/2011 | SITE - SEWER | Partial Approval | 1) 8" SDR 35 INSTALLED BETWEEN E.M. AND MH #2 2) LAYING PIPE BETWEEN MH #2 AND MH #3 |
|
09/08/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) INSTALLING 8" SDR 35 BETWEEN MH #1 AND MH #2 |
|
09/07/2011 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) 8" SDR 35 EXPOSED FOR NEW MANHOLE 2) DIGGING UPSTREAM TOWARDS MANHOLE #2 |