Permit: T11PL01089

Parcel: 11611003H


Addresses:

2656 W BROADWAY BL

Inspection Status: Approved

Inspection History: SITE - SEWER

Date Description Inspector Results Comments
03/14/2012 SITE - SEWER Approved
12/07/2011 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
09/19/2011 SITE - SEWER Partial Approval IVRS - Inspection :*
1) VACUUM TESTING MANHOLES, INSPECTING MANHOLE #2 AND MANHOLE #4 LOW PRESSURE TESTING TODAY
09/13/2011 SITE - SEWER Partial Approval IVRS - Inspection :*
1) NEED TO FINISH LOW PRESSURE TESTING
2) NEED TO FINISH VACUUM TESTING
09/12/2011 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
1) NOBODY ON SITE TO ASSIST INSPECTOR
09/09/2011 SITE - SEWER Partial Approval 1) STACK MANHOLES #2 & 3
2) BEGIN LOW PRESSURE AIR TEST
09/08/2011 SITE - SEWER Partial Approval IVRS - Inspection :*
1) STACKED MANHOLE #11,8 & 1
2) POURED MANHOLE #2 & 3
09/07/2011 SITE - SEWER Partial Approval IVRS - Inspection :*
1) 6" SDR 35 TO CLEANOUT #4 FROM MANHOLE #2
2) POURED BASES FOR #8,11 AND 1
3) SDR FROM #9 TO #3 MANHOLE AND FROM #3 TO CLEANOUT #5
09/06/2011 SITE - SEWER Partial Approval IVRS - Inspection :*
1) JENSEN STACKING FIVE MANHOLES TODAY #9,10,6,7 & 4
2) FROM MANHOLE #7 TO MH #8 8" SDR 35 OK
3) FROM MH #8 TO MH #11 OK
4) FROM MH #8 TO CLEANOUT #10 OK
5) FROM MH #11 TO MH #1 OK TO COVER SUBJECT TO VERIFICATION OF GRADE AND TEST
09/01/2011 SITE - SEWER Partial Approval IVRS - Inspection :*
ON 08/31/11 BASES POURED #9, #10
POURING #4, #6, #7 GA2 TODAY
SDR35 FROM MH#6 TO MH #4 OK TO COVER
DSR35 FROM MH#6 TO MH #7 OK TO COVER
CLEANOUTS #8 #9 INSTALLED
CLEANOUT #6, #7 INSTALLED
08/31/2011 SITE - SEWER Not ready for Inspection IVRS - Inspection :*
1) UNABLE TO LOCATE SUPER/CONTRACTOR IN JOB TRAILER AT 2 PM
08/30/2011 SITE - SEWER Partial Approval IVRS - Inspection :*
1) 8" DIP EXTENDED FROM PUBLIC MANHOLE TO MANHOLE #10
2) 8" SDR 35 FROM MH #10 TO MH #9
3) 6" SDR 35 STUBBED UP FOR CLEANOUT #11
4) 8" SDR 35 STUBBED 20' TOWARDS MH #3 FROM MH #9 8" SDR 35 EXTEND TO MH #6
5) CALL IN INSPECTIONS FOR GASES
6) ALL PIPING SUBJECT TO VERIFICATION OF GRADE AND TEST AT A LATER DATE
08/29/2011 SITE - SEWER Partial Approval IVRS - Inspection :*
1) 8" DIP EXTENDED 42' OUT OF PUBLIC MANHOLE-OK TO COVER, SUBJECT TO TEST AND VERIFICATION OF GRADE AT A LATER DATE
08/26/2011 SITE - SEWER Partial Approval 1) JENSEN WORKING ON PUBLIC MANHOLE
08/25/2011 SITE - SEWER Partial Approval IVRS - Inspection :*
WORK ON PUBLIC MANHOLE TODAY