Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date |
Description |
Inspector |
Results |
Comments |
| 03/29/2011 |
PLUMBING - GAS PRESSURE TEST |
|
Approved |
IVRS - Inspection :* |
| 03/15/2011 |
PLUMBING - GAS PRESSURE TEST |
|
Denied |
1. TEST PIPING SYSTEM IN ITS ENTIRETY. 2. PROVIDE PROOF P.E. PIPING DOES NOT GO UNDER BUILDING FOUNDATION. 3. VENT FROM WATER HEATER TO BE PROPERLY ATTACHED TO DRAFT HOOD AND VENT TO HAVE FASTENERS AT ALL JOINTS. 4. PROVIDE ONE INCH CLEARANCE FROM WOOD AT ROOF AND DOUBLE WALL VENT PIPING AT WATER HEATER. 5. PROVIDE 90 DEGREE DOWN TERMINATION ON T AND P DRAIN PIPE FOR WATER HEATER. 6. PROVIDE A GAS ISOMETRIC OF THIS SYSTEM. PROVIDE LADDER FOR ROOF TOP ACCESS TO APPLIANCES. VERIFY BONDING OF GAS SYSTEM. PROVIDE COMBUSTION AIR TO WATER HEATER. LIST MAY NOT BE COMPLETE. |