Case: T11DV07474

Parcel: 138140290


Addresses:

526 W CALLE GARCIA

Inspection Status: Approved

Inspection History: INSP - FOLLOW UP CODE ENFORCE

Date Description Inspector Results Comments
10/23/2013 INSP - FOLLOW UP CODE ENFORCE Approved The case wil be closed due to the permit has been finaled on 10-11-13. File a motion to vacate the hearing and was granted. Violation Abated, Close Case. RV.
08/14/2013 INSP - FOLLOW UP CODE ENFORCE Approved The permit has been issued, T13CM01809 on 8-13-2013 and no inspection have been done. The next court date is on 10-30-2013 at 8:30 AM. Will check the permit on 10-28-2013 to check the status. RV.
05/29/2013 INSP - FOLLOW UP CODE ENFORCE Approved Court date was changed to 6-12-13 at 2:00 PM. Did not go to the courts due to change of time and date. RV.
04/03/2013 INSP - FOLLOW UP CODE ENFORCE Approved In Court. Abatement due by 5/27/2013. Court hearing scheduled for 05/29/2013.
02/19/2013 INSP - FOLLOW UP CODE ENFORCE Approved Met with the owner and went over the plans she has done so far. They are not completed and went over what needs to be added or changed to have approved. The daughter will take over the charges and the mother will be dropped. Have court on 2-20-13 at 1:30 and 2:00. RV.
12/05/2012 INSP - FOLLOW UP CODE ENFORCE Approved Office Follow Up:
Checked permit plus and no permit has been issued and not action on the applied permit since 5-29-12. Will charge the re-fee of $75.00 for the inspection. Will do the citation and will wait for the court date to appear.
09/24/2012 INSP - FOLLOW UP CODE ENFORCE Approved Office Follow Up:
Permit has not been issued and will charge the $75.00 for the re-fee for the inspection due to no activity on having the permit approved to be issued. Will check in 30 days.
08/21/2012 INSP - FOLLOW UP CODE ENFORCE Approved Office Follow Up:
Checked Permit Plus and the permit is still in applied status and nothing since the last inspection on 5-29-12 for plan check. Will be charging the re-fee of $75.00 for the inspection. No contact with the owner. Will check in 30 days.
06/25/2012 INSP - FOLLOW UP CODE ENFORCE Approved No one home and called and left a message. Permit still in applied status. RV.
05/18/2012 INSP - FOLLOW UP CODE ENFORCE Approved TALK TO THE BROTHER OF THE DAUGHTER WORKING ON THE PLANS. LET THEM KNOW THAT NOTHING HAS BEEN DONE ON APPLYING OR HAVING THE PLANS APPROVED. HE IS FINISHING THE DRAWINGS AND ADVISED THAT THE PLANS NEED TO BE SUBMITTED SOON DUE TO FINES ARE GOING TO START BEING CHARGED IF NOTHING DONE SOON. THEY WILL BE REQUIRING A D.D.O. AND ONCE THE PLANS HAVE BEEN SUBMITTED WILL NEED TO GET THE DATE AND THE GRACE PERIOD FOR THE APPEALS. HE SHOULD BE GOING TO P.D.S.D. TO CHECK IF ALL THE PLANS ARE EXCEPTABLE FOR SUBMITTING FOR THE D.D.O. WILL CHECK IN 30 DAYS. RV.
04/16/2012 INSP - FOLLOW UP CODE ENFORCE Approved OWNERS DAUGHTER HAS SOME OF THE DRAWINGS DONE AND WILL BE SUBMITTING THOSE. SHE HAS THE SITE PLAN DONE AND ELEVATION AND SHE WILL CHECK IF SHE CAN START THE D.D.O. PROCESS. SHE WILL BE GOING IN A FEW DAYS. SHE WAS HAVING TROUBLE WITH GETTING THE DETAILS AND GOT SOMEONE TO HELP HER. WILL CHECK IN 30 DAYS. RV.
02/27/2012 INSP - FOLLOW UP CODE ENFORCE Approved TALK TO FRANK RENDON AND HE WILL BE ASSISTING ON GETTING THE PERMITS. A D.D.O. WILL BE REQUIRED AND FRANK HAS JUST STARTED THE DRAWINGS. THE OWNER WAS HAVING TROUBLE GETTING THE DRAWINGS DONE AND CALLED FRANK. WILL CHECK IN 45 DAYS. RV.
01/10/2012 INSP - FOLLOW UP CODE ENFORCE Approved TALK TO THE OWNE AND SHE IS STILL WORKING ON THE DRAWINGS. SHE WILL BE SUBMITTING PLANS ON WHAT SHE HAS DONE TO CHECK IF CORRECTION ARE NEEDED FOR APPROVAL. WILL CHECK IN 45 DAYS. RV.
11/01/2011 INSP - FOLLOW UP CODE ENFORCE Approved MET WITH THE DAUGHTER OF THE OWNER AND THE PLANS ARE BEING COMPLETED. THEY HAVE APPLIED FOR THE PERMIT AND ARE MAKING CORRECTION. THE ALLEY HAS BEEN CLEANED. HAD A SIGN ON THE FENCE IN FRONT AND WAS REMOVED AFTER DISCUSSING THE RULES OF SIGNS. WENT OVER ON WHAT NEEDS TO BE DONE ONCE THE PERMIT HAS BEEN ISSUED. WILL CHECK IN 45 DAYS. RV.