Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - HYDRONIC PIPING
Permit Number - T11CM03838
Inspection Description - MECHANICAL - HYDRONIC PIPING
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/19/2013 | MECHANICAL - HYDRONIC PIPING | Approved | IVRS - Inspection :* | |
12/06/2012 | MECHANICAL - HYDRONIC PIPING | Partial Approval | 100 psi hydro test on chilled water & hot reheat piping 1st floor stair wells ok to insulate | |
11/28/2012 | MECHANICAL - HYDRONIC PIPING | Partial Approval | HOT WATER REHEAT 1ST FLOOT AREAS F+C OK TO INSULATE STILL NEED TO SEE VAV IN STAIN WELLS OK TO USE AIR HANDLERS DURING CONTSTRUCTION | |
11/16/2012 | MECHANICAL - HYDRONIC PIPING | Partial Approval | 1st floor hydronic ppiping test area e ok to insulate | |
11/13/2012 | MECHANICAL - HYDRONIC PIPING | Cancelled | IVRS - RI canceled | |
11/13/2012 | MECHANICAL - HYDRONIC PIPING | Partial Approval | 1. First floor hydronic overhead areas #A, #B, #D, and partial in #E. onehundred plus pound test OK. 2. Hydronic piping overheadd from Mechanical Room up to penthouse OK. |