Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 03/20/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
IVRS - Inspection :*9 LIGHT POLE CAISSONS, 1 FLAG POLE CAISSON- POURED- SPECIAL INSPECTION |
| 01/15/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
DOCK LEVELER PIT; DETAIL #12 PAGE S2 OK TO POUR PROGRESS AREA |
| 01/10/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
LOADING DOCK RAMP. DETAILS # 20,21 PAGE SP2-OK TO POUR PROGRESS AREA |
| 01/09/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection :* PALLATE STORAGE AREA FOOTINGS- SPECIAL INSPECTION GL:E.0/1.7-3.4- POURED *** SEE ATTACHED SHEET WEST RAMP; AS PER DETAIL #4, PAGE SP4-OK TO POUR PROGRESS AREA |
| 12/28/2012 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
RAMP & LANDING AT BUILDING DETAIL #5 PAGE S2.2 OK TO POUR PROGRESS AREAS |
| 12/27/2012 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection :* FOOTINGS FOR RAMP (WEST) AND LANDING -DETAILS #5,7; PAGE S2.2-GL:E/3.75-4.75 OK TO POUR PROGRESS AREAS |
| 12/07/2012 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
6 F4 COLUMN FOOTINGS: GL .5A/ 3.75-5.75 CART STORAGE WALL. GL: .5A/5-5.75 OK TO POUR FOOTINGS |
| 11/02/2012 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
LOADING DOCK RETAINING WALL AT GL: D.1/ 1.7-3.4 AT 6'- OK TO POUR PROGRESS AREA COLUMN FOOTINGS TO BE INSPECTED BY SPECIAL INSPECTOR- RESULTS TO BE VERIFIED |
| 11/01/2012 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
CONTINOUS FOOTINGS GL: E/3.5-5.1;E1.75 3.4 OK TO POUR PROGRESS AREA |
| 10/31/2012 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
CONTINUOUS FOOTINGS AT GL:1/A-C; A/1-6; 6/A-D.2; D.2/5.1-6; 5.1/D.2-E OK TO POUR PROGRESS AREAS |
| 10/30/2012 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
CONTINUOUS FOOTINGS AT GL: D/1-3.4 1/C-D OK TO POUR PROGRESS AREAS |