Date Description Inspector Results Comments
12/19/2012 EXCAVATION/LAYOUT REBAR & ZON Approved
10/23/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval RETAIN WALL FOOTINGS ALONG NORTH SIDE OF CAR WASH BEING INSTALLED OK
09/28/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4 EACH C4 SPREAD FOOTINGS
09/17/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3 EACH CAISSONS EAST OF MSF SLURRIED AND REDRILLED. CAGES OK, OK TO PLACE CONCRETE
09/12/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval
09/06/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval
08/29/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM PROGRESS VERY SLOW. GRANITE CONSTRUCTION FOCUSING ON CUT & FILL FOR GRADE
08/24/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2 EACH GRADE BEAMS EAST OF MCS
08/21/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM FOR OCS POLE OK TO PLACE. TDOT INSPECTOR ON SITE FOR CONTINUOUS INSPECTION.

CAISSONS FILLED WITH WATER AFTER SUNDAY'S STORM TO HAVE CAGES PULLED. THEY NEED TO BE FILLED AND REDRILLED DUE TO SILT.
08/20/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval
08/14/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CONTINUED PROGRESS ON CAISSONS OK. SETTING 1 PER DAY.
08/08/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CONTINUED WORK ON CAISSONS FOR OCS SYSTEM. SOIL CONDITIONS DO NOT ALLOW FOR LEAVING PIER OPEN FOR COT PERIODIC INSPECTION...SPECIAL INSPECTOR IS DOING CONTINUAL INSPECTION ALONG WITH INSPECTOR FROM TDOT.