Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/28/2011 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
| 11/21/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) EAST WALL AT 14' 4" AFFE-OK TO GROUT PROGRESS AREA |
|
| 11/16/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) WEST WALL TOPPED OUT AT 11' 4"; WEST AND CENTER COLUMNS TOPPED OUT AT 11' 4"; EAST COLUMN AT LEDGER HEIGHT-OK TO GROUT PROGRESS AREAS |
|
| 11/10/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) FIRST LIFT OF 48" AFFFE OK TO GROUT PROGRESS AREAS |
|
| 10/25/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) OK TO GROUT STEM WALLS AND COLUMNS (3 AT 0"-32") |