Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/16/2013 | REINFORCED MASONRY PRE-GROUT | Approved | ||
| 08/23/2012 | REINFORCED MASONRY PRE-GROUT | Partial Approval | OK FINAL LIFT AT GARAGE DOORS. OK FOR FINAL LIFT AT OFFICE |
|
| 08/02/2012 | REINFORCED MASONRY PRE-GROUT | Partial Approval | TOP OUT MASTER BEDROOM | |
| 07/23/2012 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 07/18/2012 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* OK FOR NEXT LIFT ON GARAGE WALLS ONLY 2ND LIFT OK TO GROUT |
|
| 07/17/2012 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
| 07/16/2012 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* OK 1ST LIFT OF OFFICE/EXERCISE MASTER SUITE & GARAGE |