Inspection History Details
Inspection Status: Approved
Inspection History: FIRE - FINAL
Permit Number - T11CM02579
Inspection Description - FIRE - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/23/2011 | FIRE - FINAL | Approved | ||
12/01/2011 | FIRE - FINAL | Partial Approval | 1. Repair or replace smoke duct detectors to give a clear green light on the fire alarm control panel. 2. Add lock outs on all breakers to main fire alarm panel and nac's. 3. Install exit door on the south east corner of building. 4. Install missing ceiling tiles in the following areas: IT Room x2 Security room by UPS room x1 By exit door southeast corner of building x 10 Cover hole in Fire alarm control panel room x1 5. Correct sprinkler coverage in storage by bathrooms 129 & 130. |
|
10/17/2011 | FIRE - FINAL | Partial Approval | Partial approval given to use the west half of the call area only, when calling for the final approval will need the following done or you will not pass: 1. All ceiling tiles in place throughout the building 2. Repair ceiling in communications room 3. Fire alarm panel shall be all clear showing no problems, will need to set alarm system off again for final. 4. Adjust door to server room to close at any open position. 5. Repair or replace tamper switches on the wall post indictor valves on the Westside of building. 6. All phone lines shall work to alarm panels system |
|
09/13/2011 | FIRE - FINAL | Partial Approval | Room 165 temporary training room-partial approval. | |
09/12/2011 | FIRE - FINAL | Not ready for Inspection | Not ready- phase 2 | |
08/26/2011 | FIRE - FINAL | Partial Approval | Fire approves a Temp CofO as long as the building inspector aggres. | |
08/25/2011 | FIRE - FINAL | Not ready for Inspection | Asking for temporary C of O for training only need to do the following before temp can be given: 1. Install temporary 6 inch exit signs for pathways and temporary exit doors. 2. Ceiling tiles in place above egress pathways. 3. Only panic hardware allowed on door no other device allowed. 4. Sprinkler system up a running. On a separate note will need a approved plan and permit for the FM 300 that is being installed. |