Permit: T11CM02378

Parcel: 13405118Q


Addresses:

1010 S HARRISON RD

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
11/30/2016 EXCAVATION/LAYOUT REBAR & ZON Approved
11/21/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 7 LIGHT POLE CAISSON FOOTINGS; DETAIL #11 PAGE S6.0-OK TO POUR FOOTINGS
11/16/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SITE WALL FOOTINGS: SE APPROX 125'; NORTH APPROX 50'-OK TO POUR FOOTINGS
11/14/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SITE WALL FOOTINGS OK TO POUR
11/10/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SITE WALL FOOTING FROM SOUTHWEST CORNER 260 L.F. EAST AND TRASH ENCLOSURE FOOTING OK
11/08/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 1-F3 AND 5 F4 CONCRETE COLUMN BASES
2) SITE WALL FOOTINGS AT NORTH/WEST CORNER & WEST SIDE TO SOUTHWEST CORNER OK
11/07/2011 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) RAINED OUT
10/31/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) GRADE BEAMS AND BALANCE OF BLDG FOOTINGS
10/28/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) CONTINOUS F-1 FOOTINGS AS HIGHLIGHTED IN YELLOW ON SHEET S1.0
2) CONCRETE COLUMN BASES F4 AND 1-F4 COLUMN FOOTING 10' EAST OF N/E BLDG CORNER AS HIGHLIGHTED IN YELLOW
10/26/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 11-#F-4 EXTERIOR COLUMN FOOTINGS AND ELEVATOR PIT WALLS FROM PIT FLOOR TO 5' 4" 1ST LIFT OK
10/21/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) ELEVATOR PIT, SUMP REINFORCEMENT STEEL, EXCAVATION AND LAYOUT OK