Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T11CM02378
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/30/2016 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
11/21/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 7 LIGHT POLE CAISSON FOOTINGS; DETAIL #11 PAGE S6.0-OK TO POUR FOOTINGS |
|
11/16/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) SITE WALL FOOTINGS: SE APPROX 125'; NORTH APPROX 50'-OK TO POUR FOOTINGS |
|
11/14/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) SITE WALL FOOTINGS OK TO POUR |
|
11/10/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) SITE WALL FOOTING FROM SOUTHWEST CORNER 260 L.F. EAST AND TRASH ENCLOSURE FOOTING OK |
|
11/08/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 1-F3 AND 5 F4 CONCRETE COLUMN BASES 2) SITE WALL FOOTINGS AT NORTH/WEST CORNER & WEST SIDE TO SOUTHWEST CORNER OK |
|
11/07/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) RAINED OUT |
|
10/31/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) GRADE BEAMS AND BALANCE OF BLDG FOOTINGS |
|
10/28/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) CONTINOUS F-1 FOOTINGS AS HIGHLIGHTED IN YELLOW ON SHEET S1.0 2) CONCRETE COLUMN BASES F4 AND 1-F4 COLUMN FOOTING 10' EAST OF N/E BLDG CORNER AS HIGHLIGHTED IN YELLOW |
|
10/26/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 11-#F-4 EXTERIOR COLUMN FOOTINGS AND ELEVATOR PIT WALLS FROM PIT FLOOR TO 5' 4" 1ST LIFT OK |
|
10/21/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) ELEVATOR PIT, SUMP REINFORCEMENT STEEL, EXCAVATION AND LAYOUT OK |