Permit: T11CM02248

Parcel: 13605247C

Inspection Status: Approved

Inspection History: BUILDING - FINAL

Date Description Inspector Results Comments
01/31/2012 BUILDING - FINAL Approved IVRS - Inspection :*
12/29/2011 BUILDING - FINAL Denied IVRS - Inspection :
See detailed listing on site.| 999*
11/22/2011 BUILDING - FINAL Denied IVRS - Inspection :
See detailed listing on site.| 999*
1) MAKE ALL CORRECTIONS LISTED ON 11/1/11 INSPECTION HISTORY
2) CONTRACTOR TO PAY REINSPECTION FEE PRIOR TO FINAL
3) PROVIDE CORRECT CLEARANCE FOR VENTING SYSTEM
11/01/2011 BUILDING - FINAL Not ready for Inspection IVRS - Inspection :*
1) INSTALL PER SRCC PLAN-REMOVE CROSS CONNECTION
2) PROVIDE ACCESS FOR SERVICE OF GAS WATER HEATER
3) NEW GAS WATER HEATER REQUIRES A NEW FLEX AND SOV
4) CORRECT VENTING-INSTALL B VENT IN PROPER DIRECTION OF FLOW WITH MINIMUM CLEARANCES
5) SECURE CONNECTORS, 6" CLEARANCE REQUIRED
6) INSTALL COLLAR AT PENETRATION
7) PROVIDE A COMBUSTION AIR OPENING
8) AN ELECTRICIAN IS REQUIRED TO RUN NEW WIRING
9) CORRECT DAMAGED BOX AND INSTALL CONDUIT