Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/04/2011 | BUILDING - FINAL | Approved | IVRS - Inspection :* | |
| 07/29/2011 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) SECURE FLASHINGS WITH GALV SCREWS AND SEAL PROPERLY 2) PROVIDE STUD APPROVED PIPING SUPPORTS 3) CONTRACTOR SHALL PAY A REINSPECTION FEE FOR FAILING TO COMPLY WITH PREVIOUSLY NOTED REQUIREMENTS |
|
| 07/26/2011 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) INTERIOR CORRECTIONS OK 2) ROOF FLASHINGS ARE NOT PROPERLY INSTALLED 3) PEX IS SAGGING AND DOES NOT HAVE THE MINIMUM REQUIRED CLEARANCE ABOVE ROOF |
|
| 07/21/2011 | BUILDING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* |