Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/11/2011 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 07/22/2011 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) POTABLE PIPING EXPOSED TO FREEZING TO BE INSULATED. INSULATION TO BE INSTALLED PER MANUFACTURERS INSTRUCTIONS 2) ALL PIPING TO BE SECURED AND SUPPORTED AT CORRECT INTERVALS 3) WEATHER PROOF STRUCTURE TO HAVE CORRECT WOOD MATERIAL FOR BASE PLATES 4) FLASHINGS TO BE INSTALLED CORRECTLY AND MADE WEATHER TIGHT ON ROOF 5) TUBING ON ROOF TO BE PROPERLY SUPPORTED AT CORRECT INTERVALS. NAILS DRIVEN INTO ROOF SURFACE TO BE PULLED AND ? DENIED-CONTRACTOR TO PAY REINSPECTION FEE PRIOR TO FINAL 6) WEATHER PROOF ENCLOSURE NEEDS TO BE WEATHER TIGHT ON TOP |