Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/14/2011 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* 1) TRENCH DRAINS INSTALLED OK 2) OK FOR CONCRETE |
|
| 12/12/2011 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1) SOILS TO WET FOR INSPECTION |
|
| 10/12/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) WATER TEST ALL UNDERGROUND PIPING PER REVISED SHEET P.1.0 DATED 10/6/11 PAUL ERICHEIN ENGINEER TO BE CITY APPROVED. WILL REQUIRE TEST ON TRENCH DRAINS AND CONNECTION TO THEM |
|
| 09/28/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) 6" SANITARY DRAINAGE THRU BLDG ONLY WATER TEST THRU CLEANOUT. PROVIDE DETAIL FOR RECLAIMED DRAINAGE TD-B IF DIFFERENT FROM APP. PLAN OR INSTALL PER PLAN. PROVIDE DETAIL FOR TD-C FOR NEED OF P-TRAP AS INSTALLED. RECLAIMED TRUNK PIPING WATER TEST. RECLAIMED HAS ADDITIONAL 3" PIPING REQUIRES MINIMUM RED LINE AND APP. PLANS 2) (3)-2" STUB UPS TIEING INTO 6" AT CLEANOUT AT NORTH EAST CORNER REQUIRES DETAILS FOR SANITARY DRAINAGE AND CITY APP. PLANS. PROVIDE STAMPED SEALED LETTER FOR CELLULAR CORE PVC IN PLACE OF SPEC |