Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T11CM01715
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/25/2013 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
01/28/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 5 SHADE STRUCTURE COLUMNS OK TO POUR PROGRESS AREAS | |
01/18/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* CIRCULAR PLANTER WALL- AS PER DETAIL #4, PAGE LD-3 OK TO POUR PROGRESS AREA | |
01/03/2013 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | STEM WALL FOOTING SOUTH PAVILLION AREA OK TO POUR | |
12/28/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SITE WALL FOOTING AT PAVILLION ENTRY AREA COLUMN FOOTINGS AT BEVERLY STREET ENTRANCE -OK TO POUR PROGRESS AREAS | |
12/26/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :*4 LIGHT POLE CAISSON FOOTINGS- OK TO POUR PROGRESS AREAS | |
11/09/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTING FOR MONUMENT WALL; EAST OF AMBULANCE ENTRANCE- OK TO POUR PROGRESS AREAS | |
10/20/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | STEM WALL FOOTINGS- AT EMERGENCY ROOM ENTRY AREA OK TO POUR PROGRESS AREAS | |
10/17/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PERMISSION GIVEN TO PLACE FOOTINGS FOR SMALL (<2') RETAINING WALLS WITHOUT INSPECTION. | |
10/05/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | MAIN ENTRY SITE WALL (EAST-LOW PORTIONS) OK TO POUR PROGRESS AREAS | |
10/03/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | MAIN ENTRY (EASTSIDE) MONUMENT WALL- TALL SECTIONS (2) AT 70"-OK TO POUR PROGRESS AREAS | |
09/27/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SCREEN FOOTINGS-MAIN ENTRY (EAST SIDE) DETAIL #D PAGE S19-OK TO POUR PROGRESS AREA | |
09/24/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 7 LIGHT POLE CAISSON FOOTINGS- 3 MAIN ENTRY - EASTSIDE 4 AT EMERGENCY AREA- OK TO POUR PROGRESS AREAS | |
08/28/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 5 COLUMNS AS PER DETAIL #1, PAGE S1.1 OK TO POUR COLUMNS (SHADE STRUCTURE AT MAIN ENTRY) | |
08/17/2012 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | CONTRACTOR CANCELLED | |
08/02/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 4 LIGHT POLE COLUMNS. | |
08/01/2012 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
07/27/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | MAIN ENTRY MONUMENT WALL (EAST AND WEST WALL PORTIONS) 3 COLUMNS (WEST END) OK TO POUR PROGRESS AREAS. MATTE WIRING OVER OPTIC LINES- NW CORNER- MAIN ENTRY OK TO POUR COVER. | |
07/20/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* COLUMN FOOTINGS AT MEMORIAL PARK AREA OK TO POUR FOOTINGS |
|
07/10/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
07/09/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 8 LIGHT POLE CAISSON FOOTING S OK TO POUR PROGRESS AREAS |
|
06/29/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
06/18/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* WEST PEDESTRIAL WALK-WAY BRIDGE - SLAB ON BRIDGE (#3 REBAR AT 5 3/8" X 10") OK TO POUR PROGRESSS AREA |
|
05/29/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) BRIDGE ? (2) FOR PEDISTRIAN BRIDGE AT SOUTH FO NEW PARKING GARAGE |
|
05/01/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
04/02/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) CULVERT #15, WING WALL FOOTINGS (WYATT ROAD SOUTH) OK TO POUR FOOTINGS |
|
03/30/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
03/28/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) CULVERT WING WALLS AT 6' 6" (WYATT RD) OK TO POUR PROGRESS AREAS 2) SPILL WAY (SW GARAGE AREA) DETAIL "0" PAGE 2.13 STEM WALL NORTH OF HOPI BLDG DETAIL CITY OF TUCSON OK TO POUR PROGRESS AREAS #105 |
|
03/19/2012 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* 1) CONTRACTOR CANCELLED-RAINED OUT |
|
03/12/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
03/12/2012 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
03/08/2012 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 1 LIGHT POLE CAISSON FOOTING-EAST SIDE OF ERICKSON BLDG |
|
12/01/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 4 SWITCH GEAR PADS-OK TO POUR |
|
10/20/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) INFO ONLY |