Inspection History: ELECTRIC - UNDERGROUND
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/13/2012 | ELECTRIC - UNDERGROUND | Approved | IVRS - Inspection :* | |
| 05/29/2012 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* 1) SERVICE 9.500 AL WIRE TO SWITCH GEAR OK 2) ROOMS 2023 & 2029 WALLS OK |
|
| 04/17/2012 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* ELECTRIC UNDERGROUND - PARTIAL - 19 LIGHT POLE CAISSON FOOTINGS; & UFERS ARE IN PLACE |
|
| 03/29/2012 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* | |
| 02/09/2012 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* | |
| 01/30/2012 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* 1) 3-4" FOR PHO9NE LINES FROM MAIN ROAD TO MAP ROOM; 2-1 1/4" 1 COMMUNICATIONS & POWER IN TRENCH OK 2) 2-4" COMMUNICATIONS STUBS FOR FUTURE BLDG OK 3) CONTINUATION OF WASTE WATER 2" IN DITCH OK |
|
| 01/18/2012 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* 1) COMMUNICATIONS TO THEATER PVC IN TRENCH 2" OK 2) KITCHEN AREA PVC TO SWITCH GEAR 3"-4" IN TRENCH OK 3) 2" IN PVC FROM 1042 TO 1040 STORAGE 100' IN TRENCH OK 4) FROM SWITCH GEAR TO WASTE WATER OK |
|
| 01/11/2012 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* 1) FROM PANTANO TO ANDRADA PVC IN DITCH OK |
|
| 01/06/2012 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* 1) 2-3" PHA PANTANO TO GEAR OK 2) 2 1/2" FUTURE BLDG TO EAST SWITCH GEAR OK |
|
| 12/29/2011 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* | |
| 11/30/2011 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* 1) 2 EACH 2.5" LINES, 1 EACH 1.25" LINE, 1.5" GROUND CONDUIT FROM PANEL H4A; IDF 1009-2 3" LINES; MDF 1032-2 3" LINES, 5-4" LINES FROM NORTH EASET CORNER OF BLDG; 80' OF 2" LINE AT WAST TREATMENT SITE |
|
| 11/22/2011 | ELECTRIC - UNDERGROUND | Partial Approval | UNDER SLAB FOR FITNESS AND LOCKER ROOMS OK TO COVER | |
| 11/17/2011 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* 1) L1F TO L1A FROM ELECTRICAL ROOM TO 1040 1-2" PVC OK 2) H5A TO ELECTRIC ROOM OK 3) MDF 1032 OK 4) COMMUNICATION FOR FUTURE BLDG STUB OK |
|
| 11/02/2011 | ELECTRIC - UNDERGROUND | Not ready for Inspection | IVRS - Inspection :* | |
| 11/01/2011 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* 1) POWER TO GEAR AND SOLAR STUBS SOUTHWEST CORNER OF ELECTRIC ROOM OK |
|
| 08/23/2011 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* POLE & METER BASE & PANEL FOR TEMP POWER, TRENCH TO TRANSFORM OK |