Permit: T11CM01602

Parcel: 305030180


Addresses:

12960 S HOUGHTON RD

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
10/11/2012 EXCAVATION/LAYOUT REBAR & ZON Approved
04/17/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
19 LIGHT POLE CAISSON FOOTINGS - OK TO POUR
03/20/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SITE WALL FOOTING AT KITCHEN AREA PER SITE
2) WALL SCHEDULE OK TO POUR FOOTING
03/19/2012 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) CONTRACTOR CANCELLED-RAINED OUT
02/27/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) 2 MONUMENT SIGN FOOTINGS OK TO POUR
01/05/2012 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) FOOTINGS AT GL: 0/A-C.5, A/0-2; C/0-2 OK TO POUR PROGRESS AREAS
10/27/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) COLUMN FOOTINGS 3 C1/F8 GL: D/6,7,9 2 C2/F5, GL: C.7/9; C.8/9.5, ELEVATOR PIT FOOTINGS, PLATFORM AND P.E. STORAGE AREAS, FOOTINGS, RAMP FOOTING TO STORAGE AREAS GL: C.2/5.5-6.5; C.2/5.5-C.6/5.5 INCLUSIVE AREAS; OK TO POUR PROGRESS AREAS
10/24/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) COLUMN FOOTINGS C1/F8 (3) GL: D/7, 8, 9; C3/F5, GL: C.7/11.25; C3/F8 GL: C.6/12 F1 FOOTINGS GL: D/7-9; ELEVATOR PIT NEED RFI ON CONNECT PLACEMENT OF VERTICAL REBAR; STAIRWELL FOOTINGS AT GL: N/65-7.5; 16/F.5-J OK TO POUR PROGRESS AREAS
10/17/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) COLUMN FOOTINGS C1/F8 GL: C/9-12 (4); 12/C-D (2); E/10 (1); C3/C5 (1) GL: C.6/11.2; C/F6 (1) GL: C.5/13
2) FOOTINGS: F1 & F2: GL C/8-A/10; 14/C-E/11 INCLUSIVE FOOTINGS: EXCEPT FOOTING C/9-C.2/10.8 OK TO POUR PROGRESS AREAS
10/11/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) COLUMN FOOTINGS AS MARKED PAGE 1S2.3 7-#7 COLUMN FOOTINGS AND 10-#8 COLUMN FOOTINGS OK TO POUR
10/05/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BLDG FOOTINGS & SPREAD FOOTINGS AS HIGHLIGHTED IN YELLOW ON SHEETS 152.2, 152.3 SPECIAL INSPECTION BY GRENIER ENGINEERING
09/28/2011 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) BLDG FOOTING AT SHEET 1A1.3 GRID 2.5 TO 5.5-/D-6/D TO E E/5.5 TO 2.5-2.5 D TO E
2) BLDG FOOTING AT SHEET 1S2.3 AS PER HIGHLIGHTED AREAS-OK
3) SPECIAL INSPECTION BY GRENIER ENGINEERING