Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/30/2011 | PLUMBING - PROGRESS | Approved | IVRS - Inspection :* | |
| 08/29/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 08/19/2011 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* CLOSET FLANGES OK GAS TEST OK CALL FOR MECH. INSP. |
|
| 08/18/2011 | PLUMBING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* 1. CLOSET FLANGES TO EXTEND 1/4" ABOVE FINISHED FLOOR 2. GAS GAUGE IS DEFECTIVE 3. INSULATION OVERHEAD INCOMPLETE- GAPS IN INSULATION, NO LAGGING ADHESIVE, NO TAPE. |
|
| 08/16/2011 | PLUMBING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* |