Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/19/2011 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 03/29/2011 | PLUMBING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) PIPING ON ROOF SHALL BE PROPERLY SUPPORTED OFF OF ROOF. NO J-HOOKS DIRECTLY IN ROOF 2) PROPERLY SEAL ROOF FLASHING TO ROOF 3) WATER HEATER AND STORAGE TANK ON ELEVATED STRUCTURE THAT CAN BE DAMAGED BY WATER SHALL HAVE DRIP OANS INSTALLED UNDER THEM 4) T & P AND PRESSURE RELIEF DRAINS TO BE IN VISIBLE LOCATION FOR SAFETY CONCERNS. GRAVITY DRAIN 5) PROVIDE CORRECT APPROVED CONDUIT CONNECTION FOR ELECTRIC AT WATER HEATER |