Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/06/2011 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 08/09/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) SANITARY SEWER FOR RESTROOMS AND MOP SINK-OK TO COVER |
|
| 07/27/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) ABS GREASE WASTE INSTALLED OK-OK TO COVER 2) ABS DWV IN WOMENS RESTROOK OK 3) COPPER OK 4) OK TO COVER WALLS |
|
| 07/26/2011 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1) BACK WATER VALVE BOX COVERS EXPOSED OPEN PIPING AND REMOVED FLAPPER FROM VALVE. THIS CONDITION MUST BE RESOLVED BEFORE FINAL |
|
| 07/20/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) UNABLE TO MAKE INSPECTION WITHOUT APPROVED PLAN-CONTRACTOR HELPED ME FIND PLAN 2) NOTE: AN ABS BLAKE TEE IS NOT LISTED AS A DRAINAGE FITTINGS. BLAKE TEES ARE LISTED AS A VERTICAL SURFACE WALL CLEANOUT 3) ABS DWV UNDER SLAB AT WOMENS BATHROOM OK TO COVER |