Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/15/2011 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
| 08/11/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 3RD LIFT AT 12' OK TO GROUT PROGRESS AREAS |
|
| 08/09/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 2ND LIFT ON ALL EXTERIOR WALLS OK TO GROUT |
|
| 08/02/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 1ST LIFT ON WEST, NORTH, EAST 25' ON SOUTH WALL |
|
| 07/07/2011 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) STEM WALLS MAIN ADDITION |