Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/09/2011 | ELECTRIC - FINAL | Approved | IVRS - Inspection :* | |
| 03/08/2011 | ELECTRIC - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* |
|
| 03/01/2011 | ELECTRIC - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* ROOF: 1) INSTALL WEEB LUGS PER MANUFACTURES INSTRUCTIONS 2) TIGHTEN LOOSE FITTINGS 3) PROVIDE PHYSICAL PROTECTION #8 CONDUCTOR 4) PROPERLY SUPPORT CONDUITS WITH APPROVED STRAPS-NOT TY WRAPS 5) FRAME STRUCTURE LOOSE BOLTS AND OTHERS ? 6) USE APPROVED FITTINGS FOR PV CABLES TO JUNCTION BOX 7) DO NOT STACK LUGS, CLEAN SURFACE UNDER LUG 250.12, CANNOT USE SHEET METAL THREAD SCREWS 250.8 SERVICE AND INVERTERS: 1) PROVIDE LABELING PER 690.17 2) GROUNDING ELECTRODE CONDUCTOR FOR INVERTERS TO BE PER 250.64 (E) 3) TIGHTEN LOOSE FITTINGS AND SECURE STRAPS 4) CANNOT USE WHITE AS HOT CONDUCTOR ON A/C SIDE 200.6 5) 250.8 & 250.12 6) 70 AMP BREAKER NOTE INSTALL PER CODE 690.64 (B) & PLANS |