Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/15/2012 | ENGINEERING - FINAL | Approved | PARKING LOT RESTRIPED PER THE APPROVED PLAN. AN OVERLAY ON THIS LOT WILL BE PERFORMED IN 2 MONTHS, THE SITE WILL BE REINSPECTED AT THAT TIME TOO ENSURE THAT THE STRIPING REMAINS THE SAME AT THAT TIME. | |
| 06/13/2012 | ENGINEERING - FINAL | Partial Approval | RESTRPING OF THE SITE TO BE DONE PRIOR TO APPROVING THIS SITE. OVERLAY OF THIS PARKING LOT IS EXPECTED TOO HAPPEN IN 2 MONTHS. | |
| 06/12/2012 | ENGINEERING - FINAL | Partial Approval | SEE PREVIOUS COMMENTS. | |
| 05/28/2012 | ENGINEERING - FINAL | Partial Approval | SEE PREVIOUS COMMENTS. | |
| 05/02/2012 | ENGINEERING - FINAL | Denied | 1) SEAL AND RE-STRIPE PARKING LOT PER PLAN. 2) PROVIDE WHEEL STOPS AT PARKING SPACES AS SHOWN ON PLAN. 3) PROVIDE AN ACCESSIBLE HC ROUTE AS SHOWN ON PLAN 4) PROVIDE HC PARKING PER PLAN |