Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/29/2011 | MECHANICAL - FINAL | Approved | IVRS - Inspection :* 1) AIR BALANCE OK 2) LETTER FROM ENGINEER OK |
|
| 03/17/2011 | MECHANICAL - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 03/11/2011 | MECHANICAL - FINAL | Partial Approval | IVRS - Inspection :* 1) STEP UP CONDENSATE TO 1" AFTER 1ST TEE 2) USE PURPLE PRIMER ON ALL PVC FITTINGS PRIOR TO GLUE 3) PAINT EXPOSED PVC WITH LATEX PAINT 4) SUPPORT PVC EVERY 4' 5) TERMINATE TO WITHIN 6" OF THE GROUND 6) CAP OFF VENTS 7) PERMANENTLY I.D. UNITS ON ROOF 8) AT LEAST 1 DISCONNECT WIRED BACKWARDS-CHECK ALL 9) NEED TO SEE ABOVE CEILING DUCTING 10) SCHEDULE BLDG AND ELECTRIC INSPECTIONS 11) PROVIDE AIR BALANCE REPORT FOR FINAL 12) PROVIDE A LETTER FROM ENGINEER IF CHANGING ANYTHING ON PLANS 13) 11 PSI TEST IS OK |