| 10/12/2011 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 10/07/2011 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 10/03/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) REINFORCEMENT STEEL AT INTERIOR DOCK SUMP PUMP PIT OK 2) SPECIAL INSPECTION BY TERRACON |
|
| 09/15/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) REMAINING INTERIOR BLOCK WALL FOOTING |
|
| 09/12/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) POUR BACK AT CMU WALLS ON NORH AND WEST ? ? |
|
| 08/31/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) INTERIOR BLOCK WALL FOOTINGS C-3.5 TO 7.7, 6.2-A TO C.2 3.5-A TO C.2 |
|
| 08/17/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) COLUMN DRYPACK |
|
| 07/01/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) TILT PANELS COMPLETE 12,14,15,16,17,18 AND 19 |
|
| 06/30/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) PANELS 3.4,5,20,21,22 AND 23 2) TERRACON SPECIAL |
|
| 06/21/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) PANELS 1,2,6,7,8,9,10,11 & 13 2) TERRACON SPECIAL INSPECTED |
|
| 06/07/2011 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) PERIMETER F1 & F2 FOOTINGS |