Inspection History: PLUMBING - GAS PRESS TEST FNL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/23/2011 | PLUMBING - GAS PRESS TEST FNL | Approved | IVRS - Inspection :* 1) EXTERIOR MOP SINK OK SUBJECT TO APP. PLAN 2) GAS FINAL OK |
|
| 05/20/2011 | PLUMBING - GAS PRESS TEST FNL | Not ready for Inspection | IVRS - Inspection :* | |
| 05/19/2011 | PLUMBING - GAS PRESS TEST FNL | Not ready for Inspection | IVRS - Inspection :* 1) TEST FROM NEW METER LOCATION THRU TO CAPS ON BLDG INTERIOR AND VALVES ON ROOF 2) PROVIDE REVISED CITY APPROVED GAS ISOMETRIC OF THIS ACTUAL INSTALL 3) COMPLETE PIPING TO WATER HEATER VALVE AND INSTALL ANSUL VALVE AND ALL APPLIANCE SHUT OFF VALVES 4) HAVE ALL EQUIPMENT INSTALLED WITH RESTRAINTS IF REQUIRED, RAISE METER RISER AS REQUIRED AND RETEST SYSTEM TO PRESSURE OR WITH ANSUL VALVE INSTALL 5) COMPLETE VENTING FOR EQUIPMENT |