Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/20/2011 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 06/15/2011 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1) CORRECT LEAK AND SLOPE 2) EXPOSE LOWER END |
|
| 06/09/2011 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) 4 X 3 RESTRICTION NOT ALLOWED 9" CLEARANCE REQUIRED 2) CLEANOUTS ARE REQUIRED AFTER 135 DEGREE CHANGE OF DIRECTION 3) PROVIDE PROPER ALLIGNMENT OF JOINTS 4) BACK PITCH IN SEVERAL LOCATIONS, EXPOSE TIE IN 5) CONTINUED NOT READY INSPECTIONS WILL RESULT IN REINSPECTION FEES |
|
| 06/03/2011 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1) PIPING IS TO BE SHADED-SO THAT IT IS LAID ON A FIRM BED 2) PIPING TO BE GRADED AT 2 PERCENT FOR IT'S ENTIRE LENGTH |
|
| 04/07/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) SEE NOTES FROM 04/01/11 2) SEWER CONNECTION COVERED WITHOUT INSPECTION 3) OK FOR CONCRETE INSIDE BLDG |
|
| 04/01/2011 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) SOIL PIPE INSIDE BLDG WITH TEST ONE RISER OK 2) NEED TO SEE SEWER TIE IN AND VERIFY SLOPE |
|
| 03/30/2011 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1) NOT INSTALLED PER PLAN AND NO RED LINES ON SITE |